Features:
- Independent complete-code sourcing control
- Series 90-30 output-family context
- Exact G-suffix verification required
IC693MDL741G is kept separate from other catalog numbers so quotation, label evidence, and installed records remain tied to the requested complete code.
The accessible manufacturer manual establishes a related base-family architecture as a sixteen-point sinking output arranged in two groups, but it does not establish what the G suffix changes or preserves.
A defensible match therefore depends on original label images and project evidence rather than transferring an assumed revision or substituting another Series 90-30 output by number alone.
Availability is subject to Apter Power's current inventory and sourcing confirmation.
IC693MDL741G Manuals, Datasheets, Links
Important Notice: Other accessories, manuals, cables, calibration data, software, etc. are not included with this equipment unless listed in the above stock item description. All prices are shown in USD.
IC693MDL741G Series 90-30 Discrete Output Module Specs
General
- ManufacturerGeneral Electric
- ModelIC693MDL741G
- ConditionNew Original ready stock
- Product FamilyGE Series 90-30 PLC
Important Notice: Other accessories, manuals, cables, calibration data, software, etc. are not included with this equipment unless listed in the above stock item description. All prices are shown in USD.
Complete-code acceptance record
- Label image: Capture a clear photograph showing the full requested code and all suffix markings.
- Project record: Compare the label with the approved bill of materials and hardware configuration.
- Manual limit: Do not present related base-family data as exact G-suffix proof.
- Offer review: Match the offered label to the requested complete code before approval.
Negative-logic application checks
- Current path: Confirm the installed design requires a sinking output arrangement.
- Commons: Preserve both output-group common connections from the verified terminal record.
- Load schedule: Retain operating current, inrush, polarity, and protection for every point.
- Field power: Document the external supply serving the installed output circuits.
Evidence for controlled change
- Before removal: Record the slot, terminal numbers, conductor labels, alarms, and machine state.
- Isolation: Apply the site-approved electrical and process isolation procedure.
- Return test: Prove each output and connected load against the approved test plan.
- Archive: Store label photographs, wiring results, and the final hardware configuration.